Standon Calling 2019 – 2022

Overview

Project background:

Gorilla built two bridges and two security towers at the event.

Gorilla role summary:

  • Design, installation & removal of 2 bridges and 2 security towers

Gorilla role detail:

  • Installation of 2 bridges connecting VIP festival areas and main site.
  • Installation of 2 campsite security towers.
  • 4 man team, 1 telehandler.
  • CAD drawings / Engineering

Event Work:

Liaising with the site management to develop an appropriate installation and de-rig process

Timescales involved:

  • 3 day install
  • 1 day de-rig

This was Gorilla’s 1st year working with Standon Calling

Result / Outcome:

The approach adopted by Gorilla provided a smoother install and de-rig than experienced in previous years.  The client was very happy with the result.